Council File: 11-1789-S2Subscribe via emailPrint this recordPublic Comment

Title
6th Street Viaduct Replacement Project / HNTB Corporation / Final Design and Construction Support Services Contract
Date Received / Introduced
03/01/2013
Last Changed Date
10/25/2019
Expiration Date
10/08/2021
Reference Numbers
Work Orders: E700224A; E700224L; E700224F
Contract: C-121862
City Administrative Officer Report: 0150-11439-0000
Initiated by
Board of Public Works
File Activities
Date Activity  
10/25/2019 Memorandum to File. Click to view online docs
10/08/2019 Council continued item to/for October 29, 2019 . Click to view online docs
10/01/2019 City Clerk scheduled item for Council on October 8, 2019. Click to view online docs
09/18/2019 Public Works and Gang Reduction Committee approved item(s) . Click to view online docs
09/13/2019 Public Works and Gang Reduction Committee scheduled item for committee meeting on September 18, 2019. Click to view online docs
09/04/2019 Board of Public Works document(s) referred to Public Works and Gang Reduction Committee. Click to view online docs
08/27/2019 Document(s) submitted by Mayor, as follows:

City Administrative Officer report 0150-11439-0000 , dated August 22, 2019, relative to authorizing the Board of Public works to execute Amendment No. 1 to the Agreement between the City and HNTB Corporation for final design and construction support services for Sixth Street Viaduct Replacement Project.
Click to view online docs
03/07/2013 Council action final. Click to view online docs
03/06/2013 Council adopted item forthwith. Click to view online docs
03/01/2013 City Clerk scheduled item for Council on March 6, 2013. Click to view online docs
03/01/2013 Public Works Committee waived consideration of item . Click to view online docs
03/01/2013 Board of Public Works document(s) referred to Public Works Committee. Click to view online docs
03/01/2013 Document(s) submitted by Board of Public Works, as follows:

Board of Public Works report, dated March 1, 2013, relative to the execution of a Personal Services Contract with HNTB Corporation for the final design and construction support services for the 6th Street Viaduct Replacement Project.
Click to view online docs

Scroll Vote Left Council Vote Information (2 Votes) Scroll Vote Right

Meeting Date: 10/08/2019
Meeting Type: Regular
Vote Action: Adopted to Continue
Vote Given: (10 - 0 - 5)
Member Name CD Vote
BOB BLUMENFIELD 3 YES
MIKE BONIN 11 YES
JOE BUSCAINO 15 YES
GILBERT A. CEDILLO 1 YES
MARQUEECE HARRIS-DAWSON 8 ABSENT
JOSE HUIZAR 14 YES
PAUL KORETZ 5 YES
PAUL KREKORIAN 2 ABSENT
JOHN LEE 12 YES
NURY MARTINEZ 6 ABSENT
MITCH O'FARRELL 13 YES
CURREN D. PRICE 9 YES
MONICA RODRIGUEZ 7 YES
DAVID RYU 4 ABSENT
HERB WESSON 10 ABSENT