Date |
Activity |
|
04/13/2011 |
Council action final.
|
|
04/12/2011 |
Council adopted item forthwith.
|
|
04/05/2011 |
City Clerk scheduled item for Council on April 12, 2011.
|
|
04/05/2011 |
Energy and Environment Committee approved item(s) .
|
|
04/01/2011 |
Energy and Environment Committee scheduled item for committee meeting on April 5, 2011.
|
|
03/24/2011 |
Board of Public Works document(s) referred to Energy and Environment Committee.
|
|
03/23/2011 |
Document(s) submitted by Board of Public Works, as follows:
Board of Public Works report, dated March 23, 2011, relative to the Albion Dairy Demolition and Remediation and Albion Riverside Park Project California Environmental Quality Act (CEQA) compliance and project approval.
|
|
08/26/2010 |
Council action final.
|
|
08/25/2010 |
Mayor transmitted Council File to City Clerk.
|
|
08/24/2010 |
Mayor concurred with Council action of August 13, 2010.
|
|
08/17/2010 |
Mayor transmitted file to Mayor. Last day for Mayor to act is August 27, 2010.
|
|
08/13/2010 |
Council adopted item, subject to reconsideration, pursuant to Council Rule 51.
|
|
08/13/2010 |
Energy and Environment Committee waived consideration of item .
|
|
08/12/2010 |
Energy and Environment Committee scheduled item for committee meeting on August 13, 2010.
|
|
07/19/2010 |
City Administrative Officer document(s) referred to Energy and Environment Committee.
|
|
07/16/2010 |
Document(s) submitted by City Administrative Officer, as follows:
City Administrative Officer report 0220-04598-0000, dated July 16, 2010, relative to the Proposition O Clean Water General Obligation Bond Program funding request for Albion Dairy Park Demolition and Remediation Project.
|
|
09/29/2009 |
Council action final.
|
|
09/28/2009 |
Mayor transmitted Council File to City Clerk.
|
|
09/28/2009 |
Mayor concurred with Council Action on September 22, 2009.
|
|
09/22/2009 |
City Clerk transmitted file to Mayor. Last day for Mayor to act is October 2, 2009.
|
|
09/22/2009 |
Council adopted item, subject to reconsideration, pursuant to Council Rule 51.
|
|
09/17/2009 |
City Clerk scheduled item for Council on September 22, 2009.
|
|
09/16/2009 |
Energy and Environment Committee waived consideration of item .
|
|
09/16/2009 |
City Administrative Officer document(s) referred to Energy and Environment Committee.
|
|
09/16/2009 |
Document(s) submitted by City Administrative Officer, as follows:
City Administrative Officer report 0220-03994-0021, dated September 16, 2009, relative to addendum to the Proposition O Clean Water General Obligation Bond Program regarding Albion Dairy Park property acquisition funding request, involving the transfer of funds from Taylor Yard River Park set-aside.
|
|
09/10/2009 |
City Administrative Officer document(s) referred to Energy and Environment Committee.
|
|
09/09/2009 |
Document(s) submitted by City Administrative Officer, as follows:
City Administrative Officer report 0220-03994-0021, dated September 9, 2009, relative to the Proposition O, Clean Water General Obligation Bond Program regarding Albion Dairy Park property acquisition funding request, involving the transfer of funds from Taylor Yard River Park set-aside.
|
|
04/10/2009 |
File closed.
|
|
04/08/2009 |
Mayor transmitted Council File to City Clerk.
|
|
04/08/2009 |
Mayor concurred with Council action of April 1, 2009.
|
|
04/03/2009 |
City Clerk transmitted file to Mayor. Last day for Mayor to act is April 13, 2009.
|
|
04/01/2009 |
Council acted on Report; pending Mayors Concurrence.
|
|
03/26/2009 |
City Clerk scheduled item for Council on April 1, 2009.
|
|
03/24/2009 |
Energy and Environment Committee approved item(s) .
|
|
03/20/2009 |
Energy and Environment Committee scheduled item for committee meeting on March 24, 2009.
|
|
03/18/2009 |
City Administrative Officer document(s) referred to Energy and Environment Committee.
|
|
03/17/2009 |
Document(s) submitted by City Administrative Officer, as follows:
City Administrative Officer report 0220-03994-0017, dated March 16, 2009, relative to the Proposition O, Clean Water General Obligation Bond Program - Financial Review, Project Adjustment and Funding Recommendations.
|
|