Title
Sylmar Ground Return System Replacement Project Ordinance
Date Received / Introduced
06/08/2016
Last Changed Date
12/09/2016
Expiration Date
11/22/2018
Reference Numbers
Resolution: 016 297
City Attorney Report: R16-0289
Charter Sections: 371(b); 373 and 674(a)(1)
Ordinance: 184600
Initiated by
Board of Water and Power Commissioners
File Activities
Date Activity  
12/09/2016 Council action final. Click to view online docs
12/07/2016 Mayor transmitted file to City Clerk. Ordinance effective date: December 12, 2016.
11/29/2016 City Clerk transmitted file to Mayor. Last day for Mayor to act is December 9, 2016.
11/22/2016 Council adopted item, subject to reconsideration, pursuant to Council Rule 51. Click to view online docs
11/09/2016 City Clerk scheduled item for Council on November 22, 2016. Click to view online docs
11/02/2016 Energy and Environment Committee approved item(s) . Click to view online docs
10/28/2016 Energy and Environment Committee scheduled item for committee meeting on November 2, 2016. Click to view online docs
10/19/2016 Energy and Environment Committee continued item to/for date to be determined due to meeting cancellation. Click to view online docs
10/14/2016 Energy and Environment Committee scheduled item for committee meeting on October 19, 2016. Click to view online docs
09/15/2016 City Attorney document(s) referred to Energy and Environment Committee. Click to view online docs
09/14/2016 Document(s) submitted by City Attorney, as follows:

City Attorney report R16-0289, dated September 14, 2016, relative to a draft ordinance for the Sylmar Ground Return System Replacement project requesting to establish engineer-procure-construct criteria pursuant to City Charter.
Click to view online docs
06/08/2016 Board of Water and Power Commissioners document(s) referred to Energy and Environment Committee. Click to view online docs
06/08/2016 Document(s) submitted by Board of Water and Power Commissioners, as follows:

Board of Water and Power Commissioners report, dated June 8, 2016, relative to Board Resolution No. 016 297 which approves the Sylmar Ground Return System Replacement Project Ordinance requesting to establish an Engineer, Procure and Construct Criteria pursuant to Section 371(b) of the City Charter.
Click to view online docs

Scroll Vote Left Council Vote Information (3 Votes) Scroll Vote Right

Meeting Date: 11/22/2016
Meeting Type: Regular
Vote Action: Adopted
Vote Given: (11 - 0 - 4)
Member Name CD Vote
 (VACANT) 7 ABSENT
BOB BLUMENFIELD 3 YES
MIKE BONIN 11 YES
JOE BUSCAINO 15 YES
GILBERT A. CEDILLO 1 YES
MITCHELL ENGLANDER 12 YES
MARQUEECE HARRIS-DAWSON 8 YES
JOSE HUIZAR 14 YES
PAUL KORETZ 5 ABSENT
PAUL KREKORIAN 2 ABSENT
NURY MARTINEZ 6 ABSENT
MITCH O'FARRELL 13 YES
CURREN D. PRICE 9 YES
DAVID RYU 4 YES
HERB WESSON 10 YES