Council File: 19-1017Subscribe via emailPrint this recordPublic Comment

Title
United States Department of Energy Western Area Power Authority / Mead Substation / Agreement
Date Received / Introduced
09/03/2019
Last Changed Date
12/18/2019
Expiration Date
12/03/2021
Reference Numbers
Board Resolution: 020 019
City Attorney Report: R19-0290
Ordinance 186489
Initiated by
Board of Water and Power Commissioners
File Activities
Date Activity  
12/18/2019 Council action final.
12/18/2019 Ordinance posted/published. Ordinance effective date: December 23, 2019.
12/13/2019 Mayor transmitted Council File to City Clerk.
12/11/2019 City Clerk transmitted Council File to Mayor. Last day for Mayor to act is 12/23/2019.
12/10/2019 Council adopted item forthwith. Click to view online docs
12/03/2019 City Clerk scheduled item for Council on December 10, 2019. Click to view online docs
11/05/2019 Energy, Climate Change, and Environmental Justice Committee approved item(s) . Click to view online docs
11/01/2019 Energy, Climate Change, and Environmental Justice Committee scheduled item for committee meeting on November 5, 2019. Click to view online docs
09/10/2019 City Attorney document(s) referred to Energy, Climate Change, and Environmental Justice Committee. Click to view online docs
09/10/2019 Document(s) submitted by City Attorney, as follows:

City Attorney report R19-0290, dated September 10, 2019, relative to a draft Ordinance approving the Agreement for the operation, maintenance, replacement, ownership and interconnections at Mead Substation (Eldorado Mead OM and R Agreement), and delegating limited authority for the Board of Water and Power Commissioners to amend the Agreement.
Click to view online docs
09/04/2019 Board of Water and Power Commissioners document(s) referred to Energy, Climate Change, and Environmental Justice Committee. Click to view online docs
09/03/2019 Document(s) submitted by Board of Water and Power Commissioners, as follows:

Board of Water and Power Commissioners report, dated August 28, 2019, relative to Board Resolution No. 020 019, which approves Agreement for the operation, maintenance, replacement, ownership, and interconnections at Mead Substation between the United States Department of Energy's Western Area Power Authority and the Los Angeles Department of Water and Power, DWP No. BP 17-018.
Click to view online docs

Scroll Vote Left Council Vote Information (3 Votes) Scroll Vote Right

Meeting Date: 12/10/2019
Meeting Type: Regular
Vote Action: Adopted
Vote Given: (10 - 0 - 5)
Member Name CD Vote
BOB BLUMENFIELD 3 YES
MIKE BONIN 11 YES
JOE BUSCAINO 15 YES
GILBERT A. CEDILLO 1 ABSENT
MARQUEECE HARRIS-DAWSON 8 YES
JOSE HUIZAR 14 ABSENT
PAUL KORETZ 5 ABSENT
PAUL KREKORIAN 2 YES
JOHN LEE 12 YES
NURY MARTINEZ 6 YES
MITCH O'FARRELL 13 YES
CURREN D. PRICE 9 ABSENT
MONICA RODRIGUEZ 7 YES
DAVID RYU 4 ABSENT
HERB WESSON 10 YES