Council File: 19-1395Subscribe via emailPrint this recordPublic Comment

Title
Interconnection of the Eldorado-Harry Allen 500 kilo Volt Transmission Line / Eldorado 500 kilo Volt Switchyard / Southern California Edison Company / Nevada Power Company d/b/a NV Energy / DesertLink LLC
Date Received / Introduced
11/07/2019
Last Changed Date
02/20/2020
Expiration Date
02/05/2022
Reference Numbers
Board Resolution: 020 078
City Attorney Report: R19-0381
Ordinance 186524
Initiated by
Board of Water and Power Commissioners
File Activities
Date Activity  
02/20/2020 Council action final.
02/20/2020 Ordinance posted/published. Ordinance effective date: March 26, 2020.
02/18/2020 Mayor transmitted Council File to City Clerk.
02/07/2020 City Clerk transmitted Council File to Mayor. Last day for Mayor to act is 02/18/2020.
02/05/2020 Council adopted item, subject to reconsideration, pursuant to Council Rule 51. Click to view online docs
01/31/2020 City Clerk scheduled item for Council on February 5, 2020. Click to view online docs
01/21/2020 Energy, Climate Change, and Environmental Justice Committee approved item(s) . Click to view online docs
01/17/2020 Energy, Climate Change, and Environmental Justice Committee scheduled item for committee meeting on January 21, 2020. Click to view online docs
11/22/2019 City Attorney document(s) referred to Energy, Climate Change, and Environmental Justice Committee. Click to view online docs
11/19/2019 Document(s) submitted by City Attorney, as follows:

City Attorney report R19-0381, dated November 19, 2019, relative to a draft Ordinance approving the Agreement for Interconnection of the Eldorado-Harry Allen 500KV Transmission Line to the Eldorado 500KV Switchyard, DWP No. BP 18-010; and related actions.
Click to view online docs
11/13/2019 Board of Water and Power Commissioners document(s) referred to Energy, Climate Change, and Environmental Justice Committee. Click to view online docs
11/07/2019 Document(s) submitted by Board of Water and Power Commissioners, as follows:

Board of Water and Power Commissioners report, dated November 7, 2019, relative to an agreement for Interconnection of the Eldorado-Harry Allen 500 kilo Volt (kV) Transmission Line to the Eldorado 500 kV Switchyard among the Department of Water and Power of the City of Los Angeles, Southern California Edison Company, Nevada Power Company d/b/a NV Energy, and DesertLink, LLC.
Click to view online docs

Scroll Vote Left Council Vote Information (3 Votes) Scroll Vote Right

Meeting Date: 02/05/2020
Meeting Type: Regular
Vote Action: Adopted
Vote Given: (11 - 0 - 4)
Member Name CD Vote
BOB BLUMENFIELD 3 YES
MIKE BONIN 11 YES
JOE BUSCAINO 15 ABSENT
GILBERT A. CEDILLO 1 YES
MARQUEECE HARRIS-DAWSON 8 YES
JOSE HUIZAR 14 ABSENT
PAUL KORETZ 5 ABSENT
PAUL KREKORIAN 2 YES
JOHN LEE 12 YES
NURY MARTINEZ 6 ABSENT
MITCH O'FARRELL 13 YES
CURREN D. PRICE 9 YES
MONICA RODRIGUEZ 7 YES
DAVID RYU 4 YES
HERB WESSON 10 YES